41Project Performance International http://www.ppi-int.com/newsletter/SyEN-037.php SYSTEMS ENGINEERING NEWSLETTER brought to you by Project Performance International (PPI)

Project Performance International http://www.ppi-int.com/newsletter/SyEN-037.php SYSTEMS ENGINEERING NEWSLETTER brought to you by Project Performance International (PPI)

Add to Reading List

Source URL: www.ppi-int.com

Language: English - Date: 2011-10-23 21:14:24
42IceCube Project Monthly Report – February 2011 Accomplishments  The final IceCube summer personnel safely departed Antarctica. There are two people staying through the winter at South Pole to maintain the data manag

IceCube Project Monthly Report – February 2011 Accomplishments  The final IceCube summer personnel safely departed Antarctica. There are two people staying through the winter at South Pole to maintain the data manag

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
43IceCube Project Monthly Report - July 2008 Accomplishments • The Integrated Master Schedule is currently being revised based upon RPSC support, flight changes and station opening constraints. Currently, Drilling begins

IceCube Project Monthly Report - July 2008 Accomplishments • The Integrated Master Schedule is currently being revised based upon RPSC support, flight changes and station opening constraints. Currently, Drilling begins

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
44IceCube Project Monthly Report - November 2008 Accomplishments • Completed commissioning of the IceCube Seasonal Equipment Site and started deep ice drilling on December 3rd, two days ahead of schedule. The quick start

IceCube Project Monthly Report - November 2008 Accomplishments • Completed commissioning of the IceCube Seasonal Equipment Site and started deep ice drilling on December 3rd, two days ahead of schedule. The quick start

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
45IceCube Project Monthly Report – January 2009 Accomplishments • January was an extremely productive month for drilling and string installation. Nine holes were safely drilled in January resulting in a total of 19 str

IceCube Project Monthly Report – January 2009 Accomplishments • January was an extremely productive month for drilling and string installation. Nine holes were safely drilled in January resulting in a total of 19 str

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
46IceCube Project Monthly Report – January 2011 Accomplishments  The strings installed in December were commissioned in January and will be incorporated into the existing IceCube array during the month of February.

IceCube Project Monthly Report – January 2011 Accomplishments  The strings installed in December were commissioned in January and will be incorporated into the existing IceCube array during the month of February.

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
47IceCube Project Monthly Report – April 2009 Accomplishments • Interviews for seasonal driller positions were completed and positions filled. Support and logistical requirements for the 2009–2010 Season were submitt

IceCube Project Monthly Report – April 2009 Accomplishments • Interviews for seasonal driller positions were completed and positions filled. Support and logistical requirements for the 2009–2010 Season were submitt

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
48Search for Dark Matter from the Galactic Halo with the IceCube Neutrino Observatory – Paper Review Stephen Portillo Review of R. Abbasi et al. (IceCube Collaboration), Phys. Rev. D 84, ).

Search for Dark Matter from the Galactic Halo with the IceCube Neutrino Observatory – Paper Review Stephen Portillo Review of R. Abbasi et al. (IceCube Collaboration), Phys. Rev. D 84, ).

Add to Reading List

Source URL: portillo.ca

Language: English - Date: 2013-07-27 00:55:57
49IceCube Project Monthly Report - December 2008 Accomplishments • Drilling and string installation at the South Pole is about one week ahead of the schedule.

IceCube Project Monthly Report - December 2008 Accomplishments • Drilling and string installation at the South Pole is about one week ahead of the schedule.

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
50IceCube Project Monthly Report - November 2009 Accomplishments • Thanks to the hard work and efficiency of our team at the South Pole, drilling began three days ahead of schedule for theseason. The first str

IceCube Project Monthly Report - November 2009 Accomplishments • Thanks to the hard work and efficiency of our team at the South Pole, drilling began three days ahead of schedule for theseason. The first str

Add to Reading List

Source URL: icecube.wisc.edu

Language: English